SR542 Anderson Creek Culvert
8,000 cubic yards of load reduction fill (low density cellular concrete)
Succesful Projects
Countries Worked:
United States, Canada; Nagano, Japan; Bogota, Columbia; Manila, Philippines, Australia
of tunnels and over 741,000 Feet of small diameter pipe.
Pacific International Grout Company was contracted by Granite Construction to provide 8,000 cubic yards of load reduction fill (low density cellular concrete) for the Anderson Creek Culvert Replacement project on SR542 for the Washington State Department of Transportation.
Demolition and construction was limited to 75 calendar days to complete with liquidated damages for every day of delay. Granite created a plan to perform the work 24 hours per day. Pacific International Grout Company was able to pour three (3) pours (lifts) of 25 pcf cellular concrete per day contributing to early completion of the project.